Minor Kian Bullock Minor Kian Bullock

CBH Stage 2 - Additional Works

HTS mobilised to four remote CBH sites in WA to install improved facilities.

IMG_5881.JPG

Location: Western Australia
Client: OTOC Australia
Duration: 2 Months
Type: Modular Construction
Contract: Installation

Facility Description: The project included works on CBH facilities at 4 locations, Varley, Pingrup, Kellerberrin and Dulyalbin. All locations were improvements to CBH facilities to improve worker accommodation and facilities. These sites had been a part of an earlier project.

Works Completed: HTS was required to mobilise to each site and install additional facilities that included common rooms, offices and crib facilities. Each site was unique and required inground services, foundation preparations, concrete, veranda install and local detailed earthworks.

Read More
Kian Bullock Kian Bullock

Brookton

The Brookton project saw HTS support CDM projects and CBH Group. The works included site preparations, the installation of submains and Main Switch Board, new sewage pump station, septic and leach drain system, building foundations, installation of accommodation and amenities, concrete verandas and weather protection, testing, commissioning and preparations for occupation.

HTS was able to provide a single contractor and point of contact for all electrical, plumbing and building works.

Read More
Kian Bullock Kian Bullock

GinGin Works

HTS was contracted by CDM to provide refurbishment works for previously used accommodation and amenities modules to be used in the future. The works included internal fit out and rectification of punch list works, electrical compliance including replacement of switchboards and wiring, replacement of plumbing fittings and repair of transit damage.

These works combined multiple trades under a single contractor allowing flexibility, efficiency and an accelerated program with no lost time.

Read More
Kian Bullock Kian Bullock

Rossmoyne

Rossmoyne saw HTS provide Fleetwood’s with support to install two new modular classrooms. The works included mobilisation and preparation of the site including building foundations before landing the modules and complexing the structure. Once completed HTS connected the building to the existing services and ensured the building was safe and met Australian Standards. The building was then commissioned, cleaned and made ready for the new occupants.

A great job and very happy to be apart of the works.

Read More
Kian Bullock Kian Bullock

Golden Crown

Golden Crown was a project completed for Westgold and included the full refurbishment of an office building. The works included replacement of the air handling units, complete rewiring of electrical and data, new electrical distribution board and communications rack, replacement of fittings including lights and switches, internal fit out including new cabinetry, glazing, gyprock and painting, roofing and flashings, doors and hardware, and flooring.

The works also included external works in the form of supply, testing and commissioning of the site generator, new septic system and leech drain, water pump set and tanks and the service trenching, conduit and pipework to connect and service the building.

Read More
Kian Bullock Kian Bullock

Maragon Early Learning Centre

The Maragon Early Learning Centre was in support of Fleetwoods and required the HTS team to provide framing, finishing as well as electrical and plumbing fitout and finishing. The team was involved to provide a high quality across all trades that we could be proud of.

Read More
Kian Bullock Kian Bullock

Amrun Project Works

The Amrun projects were in support of Aqura and the works associated with the installation of LTE communication towers. Whilst as a subcontractor for Aqura, the works were on a Rio Tinto site.

The works included riggers and engineers to install LTE towers across 5 separate sites as part of the mine LTE integration plan. HTS was responsible for supervision and management of the site works to meet strict mine site requirements.

Read More
Kian Bullock Kian Bullock

Kalgan/Whaleback Communications Upgrade

The Kalgan/Whaleback communications upgrade was in support of Aqura. HTS provided advice and supervision on the underground infrastructure that was necessary to support the upgrade. The works were centered around the design and placement of communications networks including conduits and pits to ensure the upgrades were successful and met client requirements.

Read More