Nauru Mains Power Upgrade
Location: Nauru
Client: Canstruct International
Duration: 12 Months
Type: Electrical Infrastructure
Contract: Design and Install
Facility Description: The facility was located on Nauru and dependent on generators to supply electricity. There was an opportunity to connect the facility to the local HV network however modifications to the electrical infrastructure was required.
Works Completed: Having in depth knowledge of the installed infrastructure, HTS designed and manufactured a changeover board to allow the mains power to be connected. HTS also travelled to site to supervise the installation, conduct commissioning, training and handover.